Orange County Convention Center Roof Replacement Earns ABC Central Florida Eagle Award

Nov 21, 2026

At a glance: Advanced Roofing received the ABC Central Florida Excellence in Construction Eagle Award for Subcontractor Project of the Year in October 2026 for the Orange County Convention Center roof replacement in Orlando. The project replaced 1,374,000 square feet of roof, integrated a 2.2 MW DC rooftop solar array, HVAC upgrades, and 130+ rooftop fans, and finished ahead of schedule while the facility stayed open. This article covers the scope, the night-and-weekend phasing, the options an owner weighs, the codes that applied, and a pre-bid checklist for occupied public venues.

The Orange County Convention Center roof replacement earned Advanced Roofing the ABC Central Florida Excellence in Construction Eagle Award for Subcontractor Project of the Year in October 2026. Crews replaced 1,374,000 square feet of roof on the North-South Building while the convention calendar kept running and while solar, HVAC, plumbing, and life-safety trades worked on the same surface. For a public venue booked years ahead, a reroof planned like a vacant-building job risks water in an exhibit hall, a disrupted show, or a second mobilization to pull and reset a solar array. This article explains how the work was sequenced, and it does not argue that every large roof needs this approach or that one contractor is the right fit for every project.

The project is a useful reference for any owner planning commercial re-roofing on an occupied building, because a hospital, airport terminal, or retail center faces the same constraints at a smaller scale. The sections below follow the order an owner meets them and end with a checklist for the next bid.

What does the ABC Central Florida Eagle Award recognize?

The Excellence in Construction Awards are an annual competition run by the Central Florida Chapter of Associated Builders and Contractors to recognize outstanding projects built by chapter members. According to ABC Central Florida’s Excellence in Construction program description, judges drawn from across the industry either tour each entry or score it from a presentation and entry book. They weigh craftsmanship, installation, planning and coordination, challenges overcome, project complexity, the safety program, and owner satisfaction. Eagle Awards go to the winning projects, and the chapter separately names a Project of the Year in its general contractor and subcontractor divisions. Advanced Roofing’s entry was selected as Subcontractor Project of the Year.

The Orange County Convention Center is a county-owned venue on International Drive in Orlando, served locally by our Central Florida commercial roofing office. The center’s May 2026 press release on its rooftop solar milestone reports roughly 200 events a year in recent years, including 115 conventions and trade shows, and that calendar was the constraint every trade planned around. The roof also carried history. In 2009 a 1 MW rooftop photovoltaic system was completed over the center’s south concourse, and the U.S. Department of Energy described that system as the largest rooftop PV system in the southeast United States at the time. The same release states that the 2024 infrastructure upgrade replaced both the aging rooftop and the original solar panels, so the roof and the array had to be planned as one project.

What did the Orange County Convention Center roof replacement include?

The roof replacement covered 1,374,000 square feet across multiple roof elevations on the North-South Building, between 80 and 100 feet above grade. Advanced Roofing and sister company Advanced Green Technologies were selected through a competitive public bid, according to the project record published by Advanced Green Technologies. The new roof is an 80-mil PVC single-ply membrane over 2-inch polyisocyanurate insulation, held down with an induction-welded plate system. Induction welding fuses the underside of the membrane to coated plates that already secure the insulation, so the field of the sheet is attached without fasteners driven through it and the seams do not carry the whole wind load along each lap.

Water management was rebuilt along with the membrane. More than 300 roof drains were replaced and new overflow scuppers were added, because on a roof this large one slow drain lets water spread across a wide area before anyone sees it from below. Our guide to commercial roof drainage and ponding water in Florida covers that mechanism in more detail. Perimeter flashings, parapet caps, and edge metal were installed to ES-1, the wind-resistance test standard for low-slope roof edges published by SPRI as ANSI/SPRI/FM 4435/ES-1, and our article on roof edge metal and ES-1 perimeter securement explains why the perimeter gets that attention. Lightning protection was enhanced as part of the work, which on a reroof means detaching, resetting, and recertifying the lightning protection system around the new membrane.

Scope element What was installed Why it mattered on an occupied venue
Roof membrane 80-mil PVC single-ply, induction-welded attachment, over 2-inch polyiso insulation Sections could be opened, insulated, and closed within one work shift
Drainage 300+ roof drains replaced; new overflow scuppers Lowers the risk of ponding and leaks over exhibit halls
Roof edge Flashings, parapet caps, and edge metal to ANSI/SPRI/FM 4435/ES-1 Edge systems are tested for wind resistance at the perimeter
Mechanical HVAC upgrades, including 130+ rooftop fans Each curb and penetration flashed into the new membrane
Solar 2.2 MW DC array by Advanced Green Technologies, same footprint as the original Installed zone by zone after the membrane was complete
Life safety and plumbing Fire alarm and lightning protection enhancements; full drain replacements Trades sequenced so no system was left disconnected during an event

How do you replace a roof on a convention center that cannot close?

A building that hosts back-to-back shows leaves an owner four realistic ways to replace a roof, and each one carries a cost that should be visible before bid day. On this project, daytime roofing during major events was prohibited, so the choice came down to how much risk the owner would carry in exchange for speed, and how the existing solar array would be handled.

Approach How it works Where it fits Where it falls short
Phased tear-off on day shifts Sections removed and replaced during normal working hours Vacant or lightly used buildings Noise, odor, and hoisting over live events; not permitted on this project
Phased tear-off on nights and weekends (used here) Work windows set around the event calendar; each section closed before crews leave Occupied venues with fixed calendars Lower daily production, night lighting and staffing cost, tighter weather margin
Recover over the existing roof New membrane installed over the existing assembly Dry, adhered roofs with a single existing covering Prohibited by the Florida Building Code in listed conditions; can trap moisture; leaves old drains and the original array in place
Coating or restoration Liquid-applied coating over the existing membrane Roofs with years of service left and dry insulation No fix for wet insulation or failed drains; a coating warranty is not a new-roof warranty

The night-and-weekend phased tear-off was the slowest option per shift and the hardest to staff. It was also the only option that kept the event calendar intact while replacing the drainage, the edge metal, and the solar array on one schedule. Owners weighing the same decision should ask their roof consultant to core and moisture-survey the existing roof first, because wet insulation found during construction turns a recover or coating plan into a tear-off after the budget is set. A statewide contractor organized for night work on occupied buildings is also not always the lowest bid on a smaller or simpler roof, and a building with a flexible schedule may not need this level of phasing at all.

What drove the schedule on a 1.37 million square foot reroof?

The schedule was set by the event calendar, roof height, weather, and the order of trades, and none of those drivers shows up in a square-foot price. The project record lists 30 to 40 crew members on the roof daily, working in windows chosen around show move-ins and move-outs. Every pallet of insulation and every roll of membrane had to be hoisted 80 to 100 feet, and hoisting near public entrances had to be timed around pedestrian traffic.

Driver Project condition Effect on schedule Source
Event calendar About 200 events a year, including 115 conventions and trade shows Roofing limited to nights, weekends, and open dates OCCC press release, May 2026
Roof area 1,374,000 sq ft Work divided into sections sized to close in one shift Advanced Roofing project data
Height Roof elevations from 80 to 100 ft Hoisting plan and staging away from entrances AGT project record
Crew size 30 to 40 crew members daily Night supervision and lighting for every active zone AGT project record
Solar sequence 2.2 MW DC array installed after the membrane Each zone released to solar only when roofing was complete OCCC press release, May 2026
Weather Daily monitoring; exposed areas sealed before rain Opening size limited by the forecast each shift AGT project record

Advanced Roofing completed the project ahead of schedule. On a public building, finishing early has a specific value. Every week removed from the end of the job is a week the facility staff no longer has to manage barricades, separate trade entrances, and rooftop access around live events.

What changes when a Florida building stays open during a reroof?

On an occupied building, the roofing plan is a public-safety plan first. At the convention center, trades used separate access points so roofing, solar, and mechanical crews did not cross paths with each other or with attendees, and barricades separated every work area from public space. Perimeter fall restraint was provided with clamp-on guardrail systems along the roof edges, and crews completed OSHA 10 and OSHA 30 training along with fall-protection, ladder, and equipment training. OSHA’s construction fall-protection standard, 29 CFR 1926.501, requires protection for roofing work on low-slope roofs with unprotected sides or edges 6 feet or more above a lower level, using guardrails, safety nets, or personal fall arrest, alone or combined with a warning line.

Sequencing protected the building as much as the people. Each section was opened only as far as the crew could insulate, cover, and close before the shift ended, so no exhibit hall sat under open roof during a show. The project record reports zero event disruptions. Solar Power World’s April 24, 2026 report on the project noted that the roofing work required coordination to execute within an occupied, fully operational building. Before each show moved in, event staff were told which roof areas were active and which entrances had overhead work. The same discipline applies to hotel and resort roof replacement around guests, at a smaller scale.

Aerial view of the Orange County Convention Center North-South Building in Orlando with its white PVC roof and rooftop solar array

Solar coordination added a second layer. The original array had to come off before tear-off, and the new 2.2 MW DC array could go on only after a roof zone was complete, so roofing and solar crews worked a rolling handoff across the building. Advanced Green Technologies reports that the new array more than doubles the center’s onsite solar production within the same rooftop footprint and uses a custom combiner configuration to carry DC runs of 700 to 800 feet. Rooftop solar adds penetrations and load that must be coordinated with the roof system and its warranty, so conductor routes and attachment points were planned before the membrane went down.

Which codes and standards applied, and what changes on December 31, 2026?

Permit applications submitted before the end of 2026 generally follow the Florida Building Code, 8th Edition (2023), in effect since December 31, 2023. As of November 2026, the Florida Building Commission has set December 31, 2026 as the effective date of the 9th Edition (2026), and the permit application date generally determines which edition governs. Owners planning a large reroof in 2027 should ask their roof consultant and building official which edition will apply.

Orange County sits outside the High-Velocity Hurricane Zone, which covers Miami-Dade and Broward counties, so a roof in Orlando is designed under the code’s standard roofing provisions. Roof edge systems are tested to ES-1, which SPRI notes is required by the International Building Code, the model code the Florida Building Code is built on. This project was awarded through a competitive public bid, and public owners can also buy through cooperative purchasing contracts for government roofing. None of this is a code or procurement determination for a specific building. Those decisions belong to the engineer of record, the building official, and the owner’s procurement counsel.

What should a public owner ask before bidding a reroof on an occupied venue?

A reroof on an occupied venue is won or lost in the bid documents. Each item below is assigned to the role that should own it, so the list can go straight into a capital planning meeting.

  • Facility director: export the next 12 to 24 months of events and mark the move-in and move-out days when no rooftop work, hoisting, or deliveries can happen.
  • Roof consultant: core and moisture-survey the existing assembly before the documents are final, so the scope states which insulation stays.
  • Capital projects manager: decide whether solar, HVAC curbs, drains, and lightning protection sit in one contract or several, and name who owns coordination.
  • Procurement officer: require each bidder to submit a phasing plan, a night-work staffing plan, and a daily dry-in procedure with the bid so they can be scored.
  • Safety manager: require a written perimeter fall-protection plan and separated public routes beneath every area of overhead work.
  • Event operations manager: set the notice period for every change in active roof area, crane or lift use, and entrance closure.
  • Owner or asset manager: ask the roofer and solar contractor for one combined schedule showing when each roof zone is released to the array.

Frequently Asked Questions

What award did Advanced Roofing win for the Orange County Convention Center?

Advanced Roofing received the ABC Central Florida Excellence in Construction Eagle Award for Subcontractor Project of the Year in October 2026. The award recognized the 1,374,000 square foot North-South Building roof replacement at the Orange County Convention Center in Orlando, coordinated with a 2.2 MW DC solar array, HVAC upgrades, and more than 130 rooftop fans.

How large was the Orange County Convention Center roof replacement?

The roof replacement covered 1,374,000 square feet on the North-South Building, at roof elevations of 80 to 100 feet. The scope included an 80-mil PVC membrane over 2-inch polyiso insulation, more than 300 new roof drains, overflow scuppers, ES-1 edge metal, HVAC upgrades with 130+ rooftop fans, and a 2.2 MW DC solar array.

Did the convention center stay open during the roof replacement?

Yes. The facility stayed fully operational. Daytime roofing during major events was prohibited, so crews worked nights, weekends, and open dates in sections that could be closed within one shift. Separate trade entrances, barricades around work areas, and daily weather monitoring kept attendees and the building protected, and the project record reports zero event disruptions.

Who installed the solar array on the Orange County Convention Center?

Advanced Green Technologies, the solar company in the Advanced family of businesses, engineered and installed the 2.2 MW DC array using Hanwha Q CELLS modules and SolarEdge inverters with power optimizers. Advanced Roofing performed the roof replacement beneath it. The new array replaced the original rooftop system and more than doubles the center’s onsite solar production within the same footprint.

Can a large commercial roof be replaced at night?

Yes, when the building’s schedule requires it and the work is planned for it. Night work needs lighting for every active zone, supervision on each shift, a hoisting plan that avoids public areas, and a rule that every opened section is closed before crews leave. Daily production is lower, so the schedule and budget should reflect it.

Should rooftop solar be replaced at the same time as the roof?

Often it makes sense when the roof and the array are both near the end of service, because removing and reinstalling an array later costs a second mobilization. The answer depends on the remaining life of each system and the roof’s structural capacity, so a roof consultant and a solar designer should evaluate both before the scope is set.

What the Eagle Award says about reroofing an occupied public building

ABC Central Florida’s judges score planning, coordination, complexity, safety, and owner satisfaction, and the Orange County Convention Center project was built on those terms. A 1,374,000 square foot roof was replaced on a venue that hosts about 200 events a year, with drains, edge metal, mechanical work, and a 2.2 MW DC solar array sequenced into the same night-and-weekend windows, and the job finished ahead of schedule. The lesson for other owners is practical. On an occupied building, the phasing plan, the dry-in rule, and the trade sequence decide whether a reroof stays invisible to the people inside, and those belong in the bid documents. The full list of the company’s recognition is on our Advanced Roofing awards page.

Written by The Technical Team at Advanced Roofing. Founded in 1983, Advanced Roofing is 100% employee-owned, with 750+ employee-owners across seven Florida locations, and was ranked the #13 largest roofing contractor in the U.S. on Roofing Contractor magazine’s 2026 Top 100 list.